Connect with us!
Cleveland Area Neighborhood Association | Cedar Rapids, Iowa
  • Home
  • News
    • Cleveland Park Playground Project
  • About Us
  • Upcoming Events
    • Facebook Events
  • Helpful Links
    • Local Business Directory
    • Derecho Disaster Relief
    • COVID-19 Resources
    • City Buses
    • City Services Directory
    • CR Schools
    • Housing Services
    • Neighborhood Services
    • Parks & Recreation
    • Rental Services
    • SAFE CR
    • Street Services
    • Utilities
    • Citizens Review Board
    • Linn County Resources
  • Contact

Paving for Progress Update | 11-4-2021

11/4/2021

 
🚧 PAVING FOR PROGRESS CONSTRUCTION UPDATE 11-4-2021 🚧

Remaining new pavement on the Chandler Street SW loop, from 20th Street to the water tower entrance, was substantially in place last week with some curbing work completed this week. Temporary pavement was also placed where new and old pavement meet and where sanitary sewer manholes were previously replaced. The temporary pavement will provide a hard surface for winter driving and maintenance.

Remaining 2021 work includes the following:
  • Placement of concrete on 20th Street, where sewer manholes were adjusted, to match the new pavement surface.
  • After the newly placed Chandler Street pavement has cured, residential driveways will be graded and paved. If weather conditions do not allow for permanent pavement, temporary pavement will be placed on driveways for over winter.
  • Disturbed areas will be graded, then topsoil and sod will be placed. If weather conditions do not allow for permanent restoration this fall, the areas will be covered with sprayed mulch to reduce erosion during the winter. 
  • Permanent signage will be placed in completed areas to allow normal through traffic during the winter months.

Remaining construction on the Chandler Street loop, between the water tower entrance and the southern intersection of 20th Street SW (Jefferson High School entrance), will begin in spring when weather allows. This work will include removal of temporary pavements, water main replacement, service line replacement, and construction of new pavement.


CONTACT INFORMATION

CONTRACTOR - new contact
Pirc-Tobin Construction
Ryan Harter
(319) 842-2130
[email protected]

CITY CONSTRUCTION MANAGER
Eric Bahl
319-286-5531
[email protected]

CITY PROJECT MANAGER
Lee Tippe
319-286-5816
[email protected]
Sign Up For Email Notifications

Comments are closed.

    Do you have some neighborhood news to share?
    Email us at
    [email protected]
    ​to get your news highlighted on our website and Facebook page.

    Picture

    Archives

    May 2025
    April 2025
    March 2025
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    November 2019
    October 2019
    September 2019
    August 2019
    July 2019
    June 2019
    May 2019
    April 2019
    March 2019
    February 2019
    January 2019
    November 2018
    October 2018
    September 2018
    August 2018
    July 2018
    June 2018
    May 2018
    April 2018
    March 2018
    February 2018
    January 2018
    December 2017
    November 2017
    September 2017
    June 2017
    May 2017
    April 2017
    March 2017
    February 2017
    January 2017
    September 2016
    April 2016
    June 2015

Powered by Create your own unique website with customizable templates.