Next week, residential driveways will be paved and finish grading of yards will begin. Also next week, the contractor will install new residential water services on Chandler Street. This process will follow the Chandler Street loop up the hill, starting at the westerly intersection with 20th Street and working toward the water tower driveway. There will be brief water service interruptions to individual homes during this time. Homeowners will be notified in advance via door hanger or direct notification.
All of this work is expected to be completed by the end of October, marking the end of 2021 construction for this project. The remaining construction along the Chandler Street SW loop will resume in 2022 when Spring weather permits.