The pavement base for the Chandler Street SW loop, from the 20th Street intersection to the water tower entrance, is completed. Topsoil placement and storm sewer intakes on 20th Street are expected to be completed this week. Residents can drive over the subbase to access their properties.
2021 construction on this project is nearly complete. There will be a temporary construction pause during the week of October 4–8 as crews gear up for a final push to complete construction.
We expect the following work to begin on October 11:
- Weather permitting, remaining pavement and driveway placement on Chandler Street SW.
- Sodding of disturbed areas on 20th Street SW.
- Sodding on the Chandler Street SW loop will follow when the area is ready.
If weather cooperates, we expect to wrap up 2021 construction by early November.
Remaining water main, storm sewer and pavement construction on the Chandler Street SW loop, from the water tower entrance to the Jefferson High School entrance, will begin when weather allows in Spring 2022.
CONTACT INFORMATION
CONTRACTOR - new contact
Pirc-Tobin Construction
Ryan Harter
(319) 842-2130
[email protected]
CITY CONSTRUCTION MANAGER
Eric Bahl
319-286-5531
[email protected]
CITY PROJECT MANAGER
Lee Tippe
319-286-5816
[email protected]