Rain last week caused slight delays in construction along Chandler Street SW. However, we remain on track to wrap up 2021 work by mid-November.
Here is work we expect will begin next week:
- Crews should start paving the Chandler Street SW loop, between 20th Street and the entrance to the water tower.
- Finish grading and sodding should be placed along 20th Street SW.
Residential driveways on Chandler Street SW, between 20th Street and the water tower entrance, will be constructed after new pavement has cured. Finish grading and sodding will follow.
Prior to Thanksgiving, crews will place temporary pavement where new and old pavement meet and where sanitary sewer manholes were previously replaced. This way the streets can be hard-surfaced for winter driving and maintenance. Remaining construction on the Chandler Street loop, between the water tower entrance and the southern intersection of 20th Street SW, will begin in spring when weather allows. This work will include removal of temporary pavements, water main replacement, service line replacement, and construction of new pavement.
CONTACT INFORMATION
CONTRACTOR - new contact
Pirc-Tobin Construction
Ryan Harter
(319) 842-2130
[email protected]
CITY CONSTRUCTION MANAGER
Eric Bahl
319-286-5531
[email protected]
CITY PROJECT MANAGER
Lee Tippe
319-286-5816
[email protected]